Do we have any control of the date used by Enscape to determine the sun position? What is the date used when we export the model in an EXE file? Are we restricted to whatever default date Enscape is using?
In addition to having the correct geolocation derived from Revit, it would be useful for the date to be controlled from within Enscape rather than using just a fixed date.
Enscape/Revit
Hi @BIMjohn , welcome to our forums, and thank you for clarifying the software package you’re using Enscape with right away! Much appreciated.
Enscape sets the correct sun angle depending on the settings you’ve set in the “Sun Settings” dialogue in Revit:
Let me know in case this doesn’t answer your question.
Mostly, this does what i want - thanks! But if we could adjust the date in the stand-alone file, that would be cool..
You could save specific dates as views in Revit and select them as Favorite Views for Enscape - then these will be available in the standalone and you can easily switch between different dates 
You can also press U/I or shift+LeftMousebutton to change the sun.
I think what BIMJohn might be suggesting, and I would +1, is for Enscape to take the geo-location from Revit as a baseline but to be able to have a control slider in the Enscape viewer for the date, independent of the view settings.
@BIMjohn and @mattendler , pardon my late response.
This has already been requested before so it’s filed as a feature request on our agenda. Through your voices I’ve added 2 further up-votes to the topic. 